Local plan scoping consultation

Search representations

Results for Richard Lomas search

New search New search

Comment

Local plan scoping consultation

Increase in housing requirements

Representation ID: 1755

Received: 17/08/2026

Respondent: Richard Lomas

Representation Summary:

1 Our concern is that the new plan is designed to deliver to enough planning permissions into 2045 based on a 5 year national house building target of 1.5m houses. Industry experts are stating that this target will not be met (and targets of this size cannot be achieved with the current national construction infrastructure) Therefore these targets will shortly be reduced by central government.
The answer would to be to take a time out on the process for 12 months, so the plan can understand and then accurately reflect the true needs going forward into 2045.

Comment

Local plan scoping consultation

Transport and infrastructure

Representation ID: 1756

Received: 17/08/2026

Respondent: Richard Lomas

Representation Summary:

2 We are also concerned that no plan has been put forward for the additional school places, leisure and medical facilities that development on this scale would create the demand for.
The answer would be to provide a comprehensive, funded proposal for schools leisure and medical facilities as part of the New plan process.

Many thanks, I hope you find this feedback constructive

Richard Lomas

Comment

Local plan scoping consultation

Increase in housing requirements

Representation ID: 1998

Received: 17/08/2026

Respondent: Richard Lomas

Representation Summary:

1 Our concern is that the new plan is designed to deliver to enough planning permissions into 2045 based on a 5 year national house building target of 1.5m houses. Industry experts are stating that this target will not be met (and targets of this size cannot be achieved with the current national construction infrastructure) Therefore these targets will shortly be reduced by central government.
The answer would to be to take a time out on the process for 12 months, so the plan can understand and then accurately reflect the true needs going forward into 2045.

Comment

Local plan scoping consultation

Transport and infrastructure

Representation ID: 1999

Received: 17/08/2026

Respondent: Richard Lomas

Representation Summary:

We are also concerned that no plan has been put forward for the additional school places, leisure and medical facilities that development on this scale would create the demand for.
The answer would be to provide a comprehensive, funded proposal for schools leisure and medical facilities as part of the New plan process.

For instructions on how to use the system and make comments, please see our help guide.